EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Guest Book Search Site Map
Atricles

Project Server 2003

Project Server 2007

Project Server 2010

Project Server 2013 Preview

 
 
Articles -> MS Project Server 2003 Limitations -> Reasons to Migrate Project Server 2007
Overview  |  Reason 1 | Reason 2  | Reason 3  | Reason 4  | Reason 5  | Reason 6  |  Reason 7   |  Reason 8 |

Reason 9 | Reason 10  | Reason 11  | Reason 12  | Reason 13  | Reason 14  |  Reason 15    | 


Reason 8: Inability to assign a task to a team rather than to multiple resources


Scenario: PM want to assign the task to Software Development team. So based on availability, team member can self-assign the task. (or) Team lead can re-assign the task to next available team member


Project Server 2003:

In Project Server 2003, PM needs to know the actual name of the resource that is going to perform the task.




Project Server 2007:

Project Server 2007 provides a Team Resource feature, enabling the PM to assign the task to a group of people. System will send the task assignments to every resource on the team. Each team member can then individually update their own progress on the tasks from PWA.