Earned Value Analysis - Example (Hands On)

Step 2 : Save Baseline

Steps:
  • On Tools menu -> Tracking -> Save Baseline
  • Click Save Baseline and the click the baseline (Ensure Baseline is the term in the Save Baseline dropdown list and the Entire Project radio button is highlighted.)
  • Press OK to save your baseline
  • Save Project Plan

Please verify the baseline information on Project Statistics window. (On Project menu -> choose Project Information -> Click on Statistics )